Light timber framing
12×4 cm studs and sole plates in certified structural timber, panelised in the workshop.

Residential building
Project data
Location
Málaga
Floor area
4.100 m²
Handover
November 2021
Construction time
26 months
Structure
Concrete
Typology
Residential building
The brief
Twenty-four homes in Málaga's ensanche district, with a ventilated facade and an A energy certification.
Mirador was our first building to earn an A energy certification. The ventilated facade with continuous insulation eliminates thermal bridges, and every home has its own independent heat-recovery unit.
On the ground floor, the units were set aside for local, neighbourhood-scale shops, following the studio's commitment to never designing buildings that feel cut off from their surroundings.

Before · During · After
The same plot at three moments. Move the control from left to right and watch the build progress across a single frame.



Drag across the image, or focus the bar and use the ← → arrows.
The reinforced concrete foundation already poured, with the structure starting to rise on top of it. It is the only moment in the whole build where anything is mixed on site.
Drag across the image, or focus the bar and use the ← → arrows.
Gallery






Timeline
Six milestones between the first machine on the plot and the handover of keys, spread across the 26 months of this build.
The home is marked out on the ground and the plot is prepared to start.
Reinforced concrete slab. The only wet element in the whole build.
The timber panels arrive from the workshop and are dry-bolted onto the slab.
Multi-layer roof and continuous external insulation: the house is closed off.
Windows, ducting and pre-installations, with the home already protected from the rain.
Finishes, final inspection and the handover of keys.
An indicative breakdown over this project's real duration. Each milestone shifts with the site, the permit and the size of the home.
Technical solutions
The building system is the same across all our homes. We always separate what is installed from what is prepared: a house that arrives with the ducting done is not the same as one that arrives with the equipment fitted.
12×4 cm studs and sole plates in certified structural timber, panelised in the workshop.
High-performance external insulation system: the thermal envelope runs outside, with no breaks and no thermal bridges.
18 mm OSB, 50 mm of high-density XPS and 15 mm OSB over the timber structure.
Thermally broken aluminium or high-performance PVC, with 4/16/4 double glazing.
Air-source heat pump, underfloor heating or ducted air. The home is handed over with the pre-installation and ducting in place.
Ducting allowed for in the design, ready for the air-renewal unit to be fitted.
Composition according to Amara's specification document.
Tell us where your plot is and what you need. We will tell you what is possible, how long it takes and what it costs.