Residencial Almendros

Residential building

Residencial Almendros

Málaga2023

Project data

Location

Málaga

Floor area

2.800 m²

Handover

February 2023

Construction time

20 months

Structure

Concrete

Typology

Residential building

The brief

The starting point

Fourteen homes arranged around a landscaped almond-tree courtyard, on a narrow urban plot.

The long, narrow plot forced a rethink of the standard residential block: instead of one compact volume, fourteen homes are arranged around a central courtyard planted with almond trees, bringing natural light and ventilation to every interior room.

The almond trees, chosen for their early blossom and low water use, mark the passing seasons in a building designed to age well.

Residencial Almendros — Residential building

Before · During · After

Drag the line and walk through the whole build

The same plot at three moments. Move the control from left to right and watch the build progress across a single frame.

Residencial Almendros — Slab and setting out
Residencial Almendros — Structure assembled
Residencial Almendros — Home handed over
DuringBefore

Slab and setting out

The reinforced concrete foundation already poured, with the structure starting to rise on top of it. It is the only moment in the whole build where anything is mixed on site.

Drag across the image, or focus the bar and use the ← → arrows.

Gallery

The finished house

General view
General view
Facade and massing
Facade and massing
Kitchen
Kitchen
Bathroom
Bathroom
Timber interior
Timber interior
Outdoor area
Outdoor area

Timeline

How the months on site break down

Six milestones between the first machine on the plot and the handover of keys, spread across the 20 months of this build.

  1. Month 1

    Setting out

    The home is marked out on the ground and the plot is prepared to start.

  2. Month 3

    Foundation

    Reinforced concrete slab. The only wet element in the whole build.

  3. Month 5

    Structure

    The timber panels arrive from the workshop and are dry-bolted onto the slab.

  4. Month 8

    Envelope

    Multi-layer roof and continuous external insulation: the house is closed off.

  5. Month 12

    Services

    Windows, ducting and pre-installations, with the home already protected from the rain.

  6. Month 18

    Handover

    Finishes, final inspection and the handover of keys.

An indicative breakdown over this project's real duration. Each milestone shifts with the site, the permit and the size of the home.

Technical solutions

What it is built with

The building system is the same across all our homes. We always separate what is installed from what is prepared: a house that arrives with the ducting done is not the same as one that arrives with the equipment fitted.

Standard

Light timber framing

12×4 cm studs and sole plates in certified structural timber, panelised in the workshop.

Standard

Continuous insulation

High-performance external insulation system: the thermal envelope runs outside, with no breaks and no thermal bridges.

Standard

Multi-layer roof

18 mm OSB, 50 mm of high-density XPS and 15 mm OSB over the timber structure.

Standard

Windows and glazing

Thermally broken aluminium or high-performance PVC, with 4/16/4 double glazing.

Prepared

Climate control

Air-source heat pump, underfloor heating or ducted air. The home is handed over with the pre-installation and ducting in place.

Prepared

Mechanical ventilation

Ducting allowed for in the design, ready for the air-renewal unit to be fitted.

Composition according to Amara's specification document.

Want a house like this one?

Tell us where your plot is and what you need. We will tell you what is possible, how long it takes and what it costs.